Thursday, July 5, 2012

Revisions, etc...

In true PNW fashion, the rain held on tight right up until Independence Day, so the Doolittle crew decided to play it safe and not start laying oil and rock until Thursday morning. In order to make up for the delay, they will be working on Saturday, July the 7th, and the amended schedule is posted on the right. The biggest impact days will be (at this time) July 6th & 11th.  Case Road from 183rd to 113th on Friday the 6th, and 113th from Littlerock to 1-5, and Littlerock Rd from 128th to 93rd on the 11th,. Watch our Twitter Feed for updates @TCPWProjects